Bleeding during concreting of a newly placed slab connected to an existing slab will cause which surface condition?

Prepare for the CSLB Concrete C-8 License 2 Exam. Use flashcards and multiple choice questions, each with hints and explanations. Get ready for your concrete licensing exam today!

Multiple Choice

Bleeding during concreting of a newly placed slab connected to an existing slab will cause which surface condition?

Explanation:
Bleeding is the upward movement of water to the surface during fresh concrete placement. When a new slab is placed against an existing one, the joint is restrained, and the surface layer that forms from bleeding becomes relatively weak because of the laitance and the extra water in the top zone. As the concrete continues to cure and shrink, the restrained surface cannot accommodate the movement as well as the interior, so tensile stresses develop at the joint. This combination of a weak surface layer and restrained shrinkage commonly leads to cracking along the surface at the joint, rather than a uniformly smooth or evenly cured surface.

Bleeding is the upward movement of water to the surface during fresh concrete placement. When a new slab is placed against an existing one, the joint is restrained, and the surface layer that forms from bleeding becomes relatively weak because of the laitance and the extra water in the top zone. As the concrete continues to cure and shrink, the restrained surface cannot accommodate the movement as well as the interior, so tensile stresses develop at the joint. This combination of a weak surface layer and restrained shrinkage commonly leads to cracking along the surface at the joint, rather than a uniformly smooth or evenly cured surface.