If the concrete is planned for a stepped footing with the size 4' x 4' and 3' x 3' with a thickness of 8" for each step. Calculate the concrete quantity

Prepare for the CSLB Concrete C-8 License 2 Exam. Use flashcards and multiple choice questions, each with hints and explanations. Get ready for your concrete licensing exam today!

Multiple Choice

If the concrete is planned for a stepped footing with the size 4' x 4' and 3' x 3' with a thickness of 8" for each step. Calculate the concrete quantity

Explanation:
Compute concrete volume by summing the volumes of each rectangular prism that makes up the steps. Convert thickness to feet: 8 inches = 8/12 = 0.6667 ft. Bottom step: 4' × 4' with 0.6667 ft thick → 4 × 4 × 0.6667 = 10.6667 ft³. Top step: 3' × 3' with 0.6667 ft thick → 3 × 3 × 0.6667 = 6.0000 ft³. Total concrete = 10.6667 + 6.0000 ≈ 16.6667 ft³, which is about 16.57–16.67 ft³. The closest option is 16.57 ft³. If you need cubic yards, that’s 16.67 ÷ 27 ≈ 0.62 yd³.

Compute concrete volume by summing the volumes of each rectangular prism that makes up the steps. Convert thickness to feet: 8 inches = 8/12 = 0.6667 ft.

Bottom step: 4' × 4' with 0.6667 ft thick → 4 × 4 × 0.6667 = 10.6667 ft³.

Top step: 3' × 3' with 0.6667 ft thick → 3 × 3 × 0.6667 = 6.0000 ft³.

Total concrete = 10.6667 + 6.0000 ≈ 16.6667 ft³, which is about 16.57–16.67 ft³. The closest option is 16.57 ft³. If you need cubic yards, that’s 16.67 ÷ 27 ≈ 0.62 yd³.